Landfill
PLT Construction of Municipal Solid Waste
The purpose of this project is to conduct construction and installation of Landfill Power Plant with a capacity of 500 kW with Landfill Gas technology in Landfill I in Sukawinatan, Sukarami Subdistrict, Palembang City, South Sumatera Province, with scope of:
The purpose of Landfill Power Plant is to convert gas to electricity. Landfill Power Plant is divided into three main parts, which are collecting system, processing system and power generation system. On the landfill site, gas wells are constructed from drilling process. This gas will then exert gas from the process of rotting of garbage.
Landfill Power Plant is advised to be designed for :
- Detailed Engineering Design preparation of layouts, preparing component system, conduct detailed design, draw engineering design, creating Bill of Quantity, calculating technical specifications, forming work schedules and Standard Operation Procedure
- Building gas well
- Building gas collection pipes/conductor pipes
- Building collecting system and gas cooler landfill
- Building power plant
- Install connection and flow of electricity to the nearest PT PLN (Persero) on-grid system with medium voltage (20 kV) coordinating with PLN as owner
- Installing and testing equipments
- Cover soil works
The purpose of Landfill Power Plant is to convert gas to electricity. Landfill Power Plant is divided into three main parts, which are collecting system, processing system and power generation system. On the landfill site, gas wells are constructed from drilling process. This gas will then exert gas from the process of rotting of garbage.
Landfill Power Plant is advised to be designed for :
- Effectively collecting gases produced by the landfill
- Maximizing flexibility of operation from the facility
- Gas Collection Unit
- Gas Processing Unit
- Power Generation Unit
- Transmission and Distribution Unit
- Flaring Unit (Security)
- Electrical and Control System